NEW YORK (AP) -- Consolidated Edison says power will be restored everywhere in Manhattan and Brooklyn within four days, but it could be at least a week for other boroughs and Westchester County because power is delivered to those areas largely using overhead lines.

 Repairing those lines is more labor intensive.

 On Tuesday morning, ConEd said that 337,000 customers were without power in the two boroughs. There were 442,000 without power in the boroughs of Queens, Staten Island, the Bronx and Westchester County following Hurricane Sandy.

 ConEd cut power to some neighborhoods served by underground lines as the advancing storm surge from Hurricane Sandy threatened to flood substations. Floodwaters later led to explosions that disabled a substation in Lower Manhattan, cutting power tens of thousands of customers south of 39th Street.